Hi All,
Our development solution manager is completely messed up. And we are planning to upgrade solution manager from 7.1 SP6 to SP10
Our plan is to refresh dev solman to make it like prod solman & upgrade dev solman to SP10.
We never done solman refresh before & could not get much help finding related information on SDN too.
Little bit of background about our landscape.
We have 9 ECC systems in total.
2 are sanboxs', 1 training, 4 in production landscape. These 7 systems are setup in prod solman.
Another 2 systems are in project landscape & are setup in dev solman.
Solman configs are:
Need your help on solman refresh. Please clarify following questions:
1. Is it possible to refresh solman?
2. If yes, please point to right direction to find detailed info on it.
3. If not, then whats the workaround to achieve my goal without putting prod solman at risk.
let me know if more info is required.
Thanks,
Hardeep
Hi,
you can go for refresh, make sure all post refresh activity like BDLS, RFC changes and others.
Later you need to review solman_setup, we done for SM 7.0 Ehp1 refresh,our RCA, Bpmon, all custom developments all safe,
But regarding charm and cts+, you need to reconfigure the TMS setup. Please follow the guidelines here
1297727 - Change Request Management and System Copy
Thanaks
Jansi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
11 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.