Hi Gurus,

I have inspection plan group IN930004 valid from date 29.04.2011 & another group IN930207 created on 16.11.2011 & changed on 17.12.2013. I have an inspection lot created on 28.01.2014.

problem we are facing is that when in inspection lot we try to assign inspection plan by clicking on Task list/Spec group IN930004 is getting assigned to the lot. System does not display list of the groups. Our requirement is to assign group IN930207 to the lot.Multiple specifications are used in both the groups.

Pls. guide how to resolve the issue.

Regards

Amit

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member211676
Contributor
0 Kudos

Hi Amit

Could you please elaborate what is the usage for this two inspection plans and by what inspection type you are generated your inspection lot. What is the status of your inspection lot.

Regards

Kesava

Former Member
0 Kudos

Is the material assigned to IN930207?  I guess not. If you need this only change the material assignment. Remove it from IN930004 and assign it to IN930207.


~KJ~