on 02-05-2014 9:54 AM
HI
Currently we are using QGM for managing our Transports as we are in the Implementation project.
I created a project and Generated a Change Request followed by a Transport request, In the similar way we did generated different Change Requests for different Teams in the project, for EX:Generated Change request for FI Team and MM Team.
As we are in the initial phase of the project - Realization phase. we are using Transport of Copies Via QGM for moving Transport between different clients in DEV system.
once we moved on to Testing phase -All the Transported will be moved to QAS system with QGM. That means the status of the project will be in Testing phase,Is there a way in QGM that we can Generate a Transport in DEV to fix some bugs that was raised in QAS.(as this project status in Testing)
If there is no possibility in QGM for Generating Transport request in DEV which Belongs to the same Project, what would be the right approach for this,i mean like other functionality that we can use in Solution Manager to Generate a Transport Request to fix the Bug that was raised in QAS by QGM Project which is in Testing Phase.
Kind Regards,
Phaneendra
Can you check these blogs by Jansi...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your quick response Jagadish
I did followed the same blog to configure QGM.But by concern was not addressed any where in the blog.
Let me put it in another way, in ChaRM there is way that you can revert the Change Request Status from Quality Testing to Development, and it allows you generate a Transport Request, means we can use the same Change request to generate a another transport request to fix some thing in QAS. I just need to know, is there a similar way that we can revert the Change Request in QGM.
Kind Regards,
Phaneendra
Hi Phaneendra,
I never configured QGM but I read the below information .. There should be some option to create new TRs and import.
Thanks,
Jagadish.
Hi Jagadish
lets tal about the last 2 line of from your reply ," assign the changes to new transports which are imported to the test system"
how to generate a new Transport ? my question was can we generate this new transport through QGM under the same project, where the project status is already in TEST Phase.
Kind Regards,
Phaneendra K
Good Day Vivek
Thanks for the Clarification,
I was under the Impression that system doesn't allow to create a Transport request when we close the Q-Gate:Scope to Build.
I tested , It is allowing me to crate New Transport Request and New Change Request as well.
Thanks Once again.
Regards,
Phaneendra