Transportation Lanes - Transportation Duration

Former Member
0 Kudos

Team,

I’ve got Transportation Lanes that are being used for CTM and Deployment. Based on my business requirement, I’d like to use for CTM the transportation duration as 0 (zero) and 48 hours for Deployment.

Is there a way to do it?

Tks.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Bruno,

CTM will read all the Means of transport available on the lane and stock transfers will be created on the one with least Transportation cost.

Where as SNP uses only aggregate planning MOT's for planning.

You can create one detail planning MOT with "0" lead time and least Transportation cost  and another aggregate planning MOT with "48" hours lead time with Transportation cost higher that detailed planning MOT.

CTM will always choose the least cost MOT so will plan on MOT with "0" lead time.

Please try this...

Regards

Ajith Kamal