Hi all,
PP/DS Planning time fence in RRP3 (33 working days) is not as per the PTF in the Product master (20 working days). what could be the reason?
Thanks
Asim
Hi Asim.
It is possible that a user manually set the Planning Time Fence to a different date at the Product View.
If that is the case, you can select an empty line at the Elements tab and use the option "Set Planning Time Fence". If PTF was set manually, a popup will appear asking whether you want to delete it
Also, in /SAPAPO/MAT1, tab Lot-Size, check whether Periodic Lot-Size is used, whether a Planning Calendar has been specified and whether Period Factor flag has been set.
In this case, PTF will be in working days of the planning calendar and may be extended 1 period further beyond that.
Regards,
Tiago
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Asim,
Where are you seeing planning time fence of '33 working days' in //RRP3?
Best regards,
DB49
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.