on 01-31-2014 9:04 AM
Dear All,
I am creating a project in simulation version and attaching a document. now when i transfer that project to operative project by executing CJV4 the project got transfer and gets available in CJ20N. but in project builder i am unable to get the document which i had attached in simulation version.
i had check my configuration in my simulation profile i had already ticked the document indicator.
Please suggest
Regards
Dheerendra
Hello Dheerendra,
Every simulation version has administrative data. Check administrative data in CJV6.
In this, when you enter version key and Project definition, check inactive Flag indicator is not tiked.
This indicator is used to stipulate that the simulation version cannot be used.i.e Inactive simulation version are neither copied nor transferred.
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dheerendra,
I think some data cannot be transferred from simultation to operative projects through CJV4. System must be issuing log for this
What is the message in that log.?
But, let other experts also comment on this.
Regards,
Amit Rajoria
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.