BCWS and BCWP not calculated

Former Member
0 Kudos

Hi PS Experts,

Kindly give solution for following below problem,

When I run CNE1 and then CNSE5 I check that my POC values

are correct, but still, BCWS and BCWP are not calculated

and maintain the value 0.

I’ve created Value category in OPI1 and assigned it to a

secondary cost element (category 61) in OPI2. Then I’ve

assigned cost element to a cost element group.

At the end, I run CNE1 and CNSE5 and BCWS and BCWP

remain with value 0.

How can I fix this?




Thanks & Regards


srikanth ajja.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Srikanth,

To make sure customization is correct, you need to run "CHECKREPORT_PROGRESSANALYSIS" . Execute it from SE38.

One common omission is that the EV cost elements are not assigned to a cost element group. You can link the EV cost elements to the cost elements used on the project plan in SPRO under the progress analysis tab.


If you are sure that your configuration is correct, please check that your objects have EV methods and the progress version assigned. Then, as a last resort, check table COSB and see if any values comes up over there or not. If not, then it is related to EV setup. If values comes up over there, then it is related to the reporting/value category setup.

Regards,

Amit

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello Srikanth,

Any updates from anybody?

Some questions

1. What value you put in POC Waight WBS Progress Tab?

2. Did you put it for all WBS element?

3. What value you put in POC Waight activities Progress Tab?

4. Did you put it for all actvities?

5. Did you see POC getting agreegated to WBS Element?

6.What measurement method you used?

Deepak