on 01-30-2014 12:19 PM
Hi All,
I made changes to factory calendar XX in ECC system and then moved those changes to the APO system. This calendar XX is assigned to a resource.
To ensure that changes are correctly reflecting, I saved the resource in the live cache once again. Resource is using external capacity profile.(i.e. ECC settings). But to my surprise I do not see resource capacity as per the changed factory calendar even though I see modified XX calendar in APO.
Then I transferred (CIFed) resources again to APO. But no use. Please let me know the correct steps to ensure that changes done in the factory calendar are reflected correctly in the resource capacity profile.
Thanks
Asim
Hi Asim,
Regeneration of the liveCache resource using transaction /SAPAPO/REST02 or the report /SAPAPO/CRES_CREATE_LC_RES
Extending the time stream using the report /SAPAPO/CRES_CAPACITY_LENGTHEN
You must use the report /SAPAPO/OM_UPGR_TSTR_CHECK for these inconsistencies.
Also refer OSS note 1318864 - Ensuring the consistency of calendars and time streams
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.