Hi All,
I am using Component Version SAP ECC 6.0.
I have Project for which "Balance of WBS XXXXXXXX is not zero" Message no. K0115.
I checked CJ88 and there is no cost for settlement. Also checked CJI3 and seems everything is Okay. Can you please let me know which is root cause for this problem so that I can analysed and find out solution?
Thank You,
Hi Swapnil,
Is there any commitment cost lying at your WBS.? I mean any open PO etc.
Please check CJI5 and also execute CNMM (Project related procurement) to trap the root cause.
Regards,
Amit Rajoria
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Swapnil,
Please refer the following link and possibilities for your solutions
Message Ko115 - Balance of WBS xxxxxxx is not zero - Toolbox for IT Groups
Regards,
Amit Rajoria
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Have you checked in CJIC? Is there any thing pending for settlement?
check in CJI3, the balance should be 0 there and in CJI5, no open items should be there.
Also check for any pending confirmations. All the activity and activity elements should be be confirmed. Use CN25.
Regards
Shishir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Swapnil,
Have u tried to set System status of WBS element to TECO. If not, please do that.
Then return unspent money on the WBS or available amount.Verify all commitments are cleared and then try doing settlement.
You can also refer below mentioned thread
http://scn.sap.com/thread/1451395
Regards
Tushar
Hi Swapnil,
There are few more solution that you can try.
Solution 1.
Execute your Settlement Profile (OKO7) and tell me what option you have used out of three option available out there as
1. To be settled in full.
2. Can be settled.
3. Not for settlement.
I think Options 2 and 3 allow you to proceed further even if some cost is lying at WBS. Try this in development client.
Solution 2.
Can you perform period end closing activities to the project. Do the settlement of your WBS and try to close.
Solution 3.
Make sure that there are not any confirmation which are due. ie. done from CN25/COFC.
Also, check whether your WBS is statistical or capital ?
Regards,
Amit Rajoria
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Solution 1:
In Settlement Profile I have - "To Be Settled in Full" radio button selected.
I can not change setting for single Project even not wanted to change settlement parameter manually in WBS Element.
Solution 2:
Period end activities (RA, Settlement etc) already run properly.
Solution 3:
I guess confirmation related error message description is different while closing Project than what I am getting now so this is also eliminated.
My scenario is not for statistical or capital WBS.Can you please suggest?
Hello Swapnil,
When you check in CJI3, is there any cost which is remaining as that needs to be settled...
If there is no cost to be settled and balance of all cost is zero, then you also need to check if there are any open commitments in CJI5 by clicking on 'Open items only'
Also check SAP note 138723 - KO115 during closing/deleting customer project
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please execute CJEN followed by CJBN and check again.Also,make sure there is no commitments existing against your project(CJI5).
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.