Hi Guys,

I have setup the QGM project.

All the phase are setup.

The project is activated also.

But its still in  " not started " phase.

How can i change the phase.

Start of the project date is already past but the project shows as not started.

TMS check is successful.

Please help to get the project started.

I have gone through RKT and the below mentioned blog as well

http://scn.sap.com/community/it-management/alm/solution-manager/blog/2011/11/07/faq-on-quality-gate-...

Regards

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

there are other blogs,

you can have demo under http://service.sap.com/rkt-solman

Please check.

Thanks

Jansi

Former Member
0 Kudos

Hi,

I have gone through the above mentioned information sources as wel.

But cant find why my project is not started yet.

If i try to create the change it shows error