on 01-27-2014 6:39 AM
Dear Experts,
I have 6 plant under one company code, one purchase organization. For the Procurement of excisable material which will used in all 6 plant I need to maintain J1ID i.e.
1. Material & chapter id Combination
2. Cenvat Determination for all the 6 plant. which is very time consuming job.
Is there any process in which I do not need to maintain the same for all plants like if I have not to put plant in Material & Chapter Id Combination & also have not to put plant in Cenvat Determination. will it be work or all the process which I am doing is standard.
Thanks
Sumit Kumar
Hi,
You have to maintain material - chapter id combination, CENVAT determination and Assesable value(if applicable) for each plant. The reason for such a design is, in some cases some of the plants may not be an excisable. Then you need not to maintain J1ID for that plant, so that Excise tab will not appear during GR.
You may use LSMW for uploading the data as suggested above.
Regards,
Sudeep.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You have to maintain material - chapter id combination, CENVAT determination and Assesable value(if applicable) for each plant. The reason for such a design is, in some cases some of the plants may not be an excisable. Then you need not to maintain J1ID for that plant, so that Excise tab will not appear during GR.
You may use LSMW for uploading the data as suggested above.
Regards,
Sameer
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please dont copy paste others' suggestion just for points sake. Suggest on your own if you know. You have copy pasted Sudeep's post which is against the forum rules. Being one year old member, I am sure, you should be knowing the forum rules where copy pasting from other source is strictly not allowed. Please adhere to forum rules.
G. Lakshmipathi
Possible in Material Master in Foreign Trade: Import Data you can maintain it... in MM02 just put material no and don't put plant just press enter and maintain all your requirements in it.
If chapter id is same for all material in all plants.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please look into the below explanation for your Queries.
Companies are required to file with the Excise authorities, a list containing the excisable finished products manufactured and the excisable input materials required for such production, to avail Modvat / Cenvat Credit.
Similarly for Subcontracting you will have to maintain the Input and Out put material under Cenvat Determination.
It is possible that an input material may be used in the production of more than one finished product. However, if such a material is mainly used for the manufacture of a particular finished product then the input material is identified to be the default material. The default indicator has to be checked in such cases.
Just donot maintain the Cenvat Determination for One Excisable Material and run the Procurement Cycle till Excise invoice Part2 posting and let us know your observations / findings.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sumit,
you need to maintain for the plants if all plants are Excisable.
regards
manu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You have to maintain for each plant to avail cenvat, if needed to can upload in mass using LSMW
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.