inspection lot planned costs and actual costs

former_member184574
Active Contributor
0 Kudos

Hi,

I have maintained activity types like setup time, inspection time in work center and also relevant formuals in scheduling view and costing view, now in the inspection plan assigned this workcenter to a operation and maintained standard hours for this operation for the particular activities...Created a inspection lot for this material...Now where to see the planned costs for this and where user will confirm the actual hours and where to see this actual costs..can any body guide...  

Thanks

Kumar

Accepted Solutions (1)

Accepted Solutions (1)

former_member211676
Contributor
0 Kudos

Hi Kumar

After this you need to go through the following steps.


1) Assign control key QM04 which is having confirmation required option in its configuration.


2) spro-> Qm -> Basic settings -> maintain settings at plant level

  in Inspection lot creation tab make sure

Order type : Ind.settlement 'QL01' and coll settlement 'QL02'.


3) spro-> Qm -> quality inspection-> inspection lot creation -> Maintain inspection types

Here assign order type QL02 for your inspection type.

4) spro-> Qm -> Environment ->Central functions-> Maintain QM order types


Here assign Cat 6 QM Order to settlement order types  QL01, QL02.

5) Then create QM order in QK01 for your material with material, Plant, Inspection type combination.

    Here enter need to enter order type QL01, controling area, cost center, Functional area, Profit center.

   After creating you can view the QM order number in MM03 for this inspection type.

6) Then after result recording while saving system will through a pop up to enter the actual consumption values of activities.

7) You can look the cost analysis in usage decision Extras-> costs.

Regards

Kesava

former_member184574
Active Contributor
0 Kudos

Hi Kesava,

Thanks for your detailed reply...

but my question is first we need to create a QM order and then we need to assign this order to inspection lot..is my understanding correct ??...one more question is same QM order is used for different inspection lots or we need to create one QM order for one inspection lot....

Thanks

Kumar

former_member211676
Contributor
0 Kudos

Hi Kumar

QM order won't be assigned to inspection lot.We have to create QM order with the combination of material, inspection type, plant. For one materials we will assign one or more inspection type correct!!!

So for each inspection type assigned in material master we have to create the QM order. QM order will be shown in MM03 once created in QK01. After this cost will calculated for this order each time when we record the results and enters the consumed activities for that inspection type.

Here to through the pop up after result recording to enter the actual activities we have to use control key QM04 for operation in inspection plan.

Regards

Kesava

former_member184574
Active Contributor
0 Kudos

Hi Kesava,

Thanks for your reply....executed one full flow and understood...still I have few questions...

1. There will not be a individual QM order for individual inspection lot....All inspection lots of a material, plant and inspection type combintion are mapped to single QM order....

2. If I want to create a single QM order for one inspection lot then how to configure it in the system...is such provision is there...

3. Once we create a QM order it is getting updated in the QM view in the corresponding inspection type in material master..How frequently this QM order is created.. like for every month or year....what the criterion..

appreaciate if you share your previous business scenarios in this....

Thanks

Kumar

former_member211676
Contributor
0 Kudos

Hi Kumar

There is no QM order for individual QM order.Qm order won't be created for inspection lot.There is no need to create separate QM orders for each inspection lot as Qm order also a master.

Regards

kesava

former_member184574
Active Contributor
0 Kudos

Hi,

Thanks for all your replies..now it is clear...but still not able to understand why SAP has not given the provision to calculate costs at individual inspection lot level..... anyway closing the thread....

Thanks

Kumar