on 01-25-2014 5:35 AM
Hi Experts,
I defined Block Planning for the FERT that are produced in a plant and I have the following 2 questions about Block Planning:
1) Block Planning can be used in APO SNP?
I see only the "Block Planning Class" in PPDS PDS, I have read that I can used Block Planning in APO SNP, but I do not know how I can do
2) If I execute the following 3 steps:
a) SNP Heuristic, it generates SNP:PL_ORD of FERT and HALB (if halb is produced in the same plant), it generates PurRqs of HALB (if halb is produced in other plant) and ROH
b) Convert SNP:PL_ORD to PlOrd, the system changes the date of PlOrd of the FERT according to the blocks defined in the resource, but does not change the PlOrd of the HALB (if halb is produced in the same plant) and PurRqs of HALB (if halb is produced in other plant) and ROH
c) PPDS Optimizer, the system changes the date of the PlOrd of the FERT according to the blocks defined in the resource to remove the heavy workload of the resource, but it does not change the date of the PlOrd and PurRqs of the components
What should be done to change the date of the PlOrd and PurRqs of the components according to the PlOrd of the FERT?
Best Regards,
Hii Arnulfo,
here are your answers...
1. Go Through the following threads
2. After Fert material planned order get rescheduled, as per the block
A. Run Rescheduling: Top Down (SAP_PP_010) , to reschedule your HALB (SFG) materials as per the scheduled Finished Good materials.
or
B. Take a multilevel heuristic run for HAlB materials to regenerate the planned order as per the FERT material scheduled orders
Regards
Debashis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi There. SNP orders with block characteristics attached example
Block planning from SNP to PPDS
Once you get the characteristic onto the material master – from the MRP3 tab in ECC for location, or from the basic tab for global, then these characteristics can be used to create APO orders in SNP which have characteristics on them to use in PPDS
and
So
So when you create an order with SNP Heuristic, then this SNP order has the characteristic attached – only because it gets it from the product master (cant see this in the SNP book but can see it when you view the SNP order in the product view)
Then when you CONVERT this SNP order into a PPDS order, then it still has the same characteristic attached and then can be used within blocks
Orders attached to the blocks (once converted to PPDS orders)
You can also use SNP optimizer to propose “suggested DATES and times” for the block dates to download (although these are only in full day blocks, and you need to adjust the BADI if you want to download block dates/times to smaller than day rates)
john
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.