Can Multiple Operators record Labor time simultaneously for the same operation in SAP ME 6.1?

Former Member
0 Kudos

Hi ME experts,

The manufacturing process followed at our plant is that multiple operators work simultaneously on the product in a single operation.

We want the labor to be tracked for each operator working on the same operation.

In ME 6.1, Can Multiple operators record their Labor efforts for a single operation at the same time?

If so how? Please let me know

Thanks

Vignesh

Accepted Solutions (1)

Accepted Solutions (1)

williamson
Advisor
Advisor
0 Kudos

Hi,

I belive they can by having each of them individually  labour on to the operation.  There are some labour rules that can be set for how to split the labour of when multiple operators have laboured on to an operation.