Dear All

we want to apply quota arrangement in planned PR of APO. now we face a problem. the minmun spliting quantity in quota arrangement setting doesn't work.

the Scenario : we want system to generate planned PR according quota arrangement only when demand quantity is exceed 100000.

SAP told us, this function is only effect in PPDS planning. But we use CTM planning. Is there any possible solution to fulfill our requirement without changing planning type ? enhancement or something like that . Thank you !!!

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member189901
Contributor
0 Kudos

Hii Bennet,

We have also get same kind of issue,Well I am not sure whether in CTM is it possible or not . But we have used ECC quot arrangement for quantity split. MRP gives  perfect result as desired...

Regards