on 01-24-2014 7:09 AM
Dear All
we want to apply quota arrangement in planned PR of APO. now we face a problem. the minmun spliting quantity in quota arrangement setting doesn't work.
the Scenario : we want system to generate planned PR according quota arrangement only when demand quantity is exceed 100000.
SAP told us, this function is only effect in PPDS planning. But we use CTM planning. Is there any possible solution to fulfill our requirement without changing planning type ? enhancement or something like that . Thank you !!!
Hii Bennet,
We have also get same kind of issue,Well I am not sure whether in CTM is it possible or not . But we have used ECC quot arrangement for quantity split. MRP gives perfect result as desired...
Regards
Debashis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.