Hi Guys,

I have 2 system landscape for solution manager

DEV-->PRD

In dev system i have 4 clients 010:020:030 and 100.

Client 100 is my configuration is client.

I have CHARM activated in 100.

In DEV we have transport setup as 010->020->030 to test the charm process.( Rfc and Urgent Change).

Now we do all the configurations in 100 client and we want to move the TRs from DEV 100 to PRD 100.

how can i set the transport routes from DEV 100 to PRD 100 ?

As already we have routes in place in dev ( 010:020:030).

Please advice.

Regards

Abhishek

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member215345
Active Participant
0 Kudos

Hi Abhishek,

For the Charm to work properly transport route should be in place and working.

1. Create transport routes with transport target groups to enable transport to multiple target clients/systems.

2. In solar_project_admin in solution manager under your CHARM project maintain one more logical component with the required source and target clients.

3. Generate maintenance cycle/task list for same.

Regards,

Jayadeep

former_member45419
Active Contributor
0 Kudos
nirmal_konchada
Active Contributor
0 Kudos

Hello,

You need to activate Extended Transport function for defining client specific trannsport routes.

https://help.sap.com/saphelp_nw04/helpdata/en/1b/9dc2d6e59911d184810000e8a57770/content.htm

Parameter is CTC = 1.

Regards,

Nirmal.K

Former Member
0 Kudos

Hi ,

Since CHARM is activated so this parameter is already in place.

I create test transports for urgent change in client 010 and move it to 020 and 030.

Charm client is 100 and all the configurations are done here and now we want a route from DEV 100 to PRD 100 .

Regards

Abhishek