on 01-24-2014 7:38 AM
Hi Guys,
I have 2 system landscape for solution manager
DEV-->PRD
In dev system i have 4 clients 010:020:030 and 100.
Client 100 is my configuration is client.
I have CHARM activated in 100.
In DEV we have transport setup as 010->020->030 to test the charm process.( Rfc and Urgent Change).
Now we do all the configurations in 100 client and we want to move the TRs from DEV 100 to PRD 100.
how can i set the transport routes from DEV 100 to PRD 100 ?
As already we have routes in place in dev ( 010:020:030).
Please advice.
Regards
Abhishek
Hi Abhishek,
For the Charm to work properly transport route should be in place and working.
1. Create transport routes with transport target groups to enable transport to multiple target clients/systems.
2. In solar_project_admin in solution manager under your CHARM project maintain one more logical component with the required source and target clients.
3. Generate maintenance cycle/task list for same.
Regards,
Jayadeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Abhishek,
Pls check below links
Configuring the Development and Production Systems - Change and Transport System - SAP Library
Regards
Nayeem
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
You need to activate Extended Transport function for defining client specific trannsport routes.
https://help.sap.com/saphelp_nw04/helpdata/en/1b/9dc2d6e59911d184810000e8a57770/content.htm
Parameter is CTC = 1.
Regards,
Nirmal.K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Think this is what you are looking for.
Kind Regards,
Johan