Hello Friends,
I am working with the PS integration with CATS and I have a requirement in CATS worklist i am able to see the network to which the resource is staffed,
but i also want to show the WBS element/Project ID and respective description to which the network is assigned.
How to achieve it. In the worklist displying only network ID and description is not enough which will not give a clear information for the users to book the time sheet.
Any advice on this will be a great help.
Regards,
Lohith
Are you doing workforce planning or Lean Staffing? How are people being assigned to the NWA?
Regardless, you will need to implement a user exit to bring in these other related fields. This is a very common enhancement.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Lohith,
In work list click on the configuration button on extreme right (enclosed the icon) of the screen. you can see a pop up on the screen, click on administrator a popup will display with all the fields which are there in work list. select the fields which you want and make them visible.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.