Hi Gurus!
I am creating a project through assembly process.
While creating, client need a new user status to block the release of network ( create a new status and block it for release), unless the GTS block is removed on the material in sales order.
Any clue and any inputs?
Regards
Hi,
What is your process of releasing sales order and project. does you release the project immediately as soon it was created or you release the object status (user status) in sales order.
any have you can have user status set up at network header/activity level and set as INIT which defaults. You can release the user status NWA after you release the sales order (GTS) and before project released.
You can refer threads which are available in this forum how to set up user status for reference.
Thanks,
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Surya,
I guess there is not linkage of release of sales order which triggers release of PS NW.
However you can refer to the following link which describes RFC functionality, if you are looking for auto release of PS NW from GTS.
User Exit to Transfer Preference Status to Feeder System - SAP Documentation
Thanks,
Sudhakar