Capacity Report issue

Former Member
0 Kudos

Hi PS Experts,

please give me relief by giving solution to this issue,

How can we set the options for capacity reports CM01 ?





Thanks & Regards


srikanth ajja.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Srikanth Ajja,

This will possible depend on your config, but the options I use are:
Settings>General>
Tick, Cumulation of Reqmts, Dyn. capacity cumul. and then select the hierarchy you have set up.
I then select the financial year (as we are budget driven) using Entry type A and the start/finish of the financial year.
I select period Month.
Then click tick.
I then select the work centre I require. or arm of the hierarchy.
You can then select standard overview and also select graphs or if you need a detailed list press that button.

I hope this will resolve your query.

Thanks & Regards

Shashank Gaur

Former Member
0 Kudos

Hi shashank,

Thanking you so much.. for giving solution, our PS team will work on this.

Thanks

srikanth ajja.