Hi PS Experts,
Could you please suggest me, we are struck in following scenario, while starting project initial stages as follow below
We are facing a problem related to Planned Revenue.
We are creating WBS element, activity and activity milestones.
These milestones are getting copied in a billing plan in Sales
order and WBS element is given in the account assignment
at item level. However, I am still not getting the planned
revenues in any of the standard PS report.
What am I doing wrong and how do I resolve this problem?
Thanks in advance.....
Thanks & Regards
srikanth ajja
Hi Ajja,
You can do the following to backtrack a little bit to review some procedures you might have missed.
1. Check the PS Planning profile, so that the flag indicating the adoption of revenue plan from the Sales documents is on.
2. You can also check the Billing element (Operative Indicator) for the WBS which you have mentioned in theSales order.
3. Check the customizing procedure for revenues:
“Planned revenues - Automatic calculation... - Update from SD”;
Regards,
Amit Rajoria
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.