How to set for a budget availability control in Former Budgeting

Former Member
0 Kudos

Hi

   I have no experience about Former Budgeting. so,

   could you explain how to set  "Deactivate / Activate Availability Control"  IMG Screen  in Former Budgeting.

    IMG menu path  : Former Budgeting > Availability Control >  Deactivate / Activate availability control

   For the budget control activating,   i am not sure whether  "fiscal year" is blank  for  all years.  also,  "Always check" is checked.

MK

3 REPLIES 3

iklovski
Active Contributor
0 Kudos

Hi,

'Always check' flag is relevant for availability control on documents chain. Press F1 on the field to have more details. It's more prudent to define fiscal year in the table; though, not having it normally should activate it for all, if I remember correctly.

Regards,

Eli

Former Member
0 Kudos

thanks for your response.

    could you give me a your advice  about the  below screen capture?

is AVC activated for  2012, 2013 ?

 

  MK

iklovski
Active Contributor
0 Kudos

I don't think so, as the system would check the years existence. If only 'blank' line would be present, then 'yes'.