on 03-15-2007 6:56 PM
Hi there
Has anyone had any experince in revising Cost Elements (& CE Groups) in Value Categories? I have a problem in that the original configuration of Value Categories had many Cost Elements assigned to a generic Value Catergory. I would like to break this down into multiple Value Categories and get rid of the generic one. I have executed programs RIPMCO00 RIPMS001after restructuring, and am not getting any results.
Thanks
Peter Docharty
Hello Peter,
pls follow the below mentioned path. You can change the settings here.
SAP Customizing Implementation Guide --> Plant Maintenance and Customer Service --> Maintenance and Service Processing --> Basic Settings --> Settings for Display of Costs --> Assign Cost Elements to Value Categories
thanks
Bala
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Bala
I have done all that stuff, however, if you check out the documentation for this transaction, it talks about restructuring files PMCO & PMCOQT by using the
RIPMCO00 program and about changing the VC if records have already been written to these files by using RIPMS001. I am curious as to whether any users have successfully changed the Cost Elements assigned to VC and their procedure.
Peter
User | Count |
---|---|