I need to control actual revenue with planned revenue entered in CJ42 against WBS element.

Please guide.

Thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member203098
Active Contributor
0 Kudos

Hi Ravi,

There is no such option to control actual revenue in standard. Instead you can think on WBS billing plan concept, plan revenues also update against the WBS element as well. Billing plan can be copied further to sales order. In invoice transaction write a technical code to validate actual revenue with reference to WBS billing plan.