Hi Guys,
During the production manufacturing phase we quite often have to update the routing with additional operations.
Today this is done manually and can be time consuming plus typo errors can occur.
I've create my Ref operation set which I would like to assign to the released production order which already has the standard routing.
TCODE CO02 --> operation overview --> select operation line -->edit --> insert Ref. operation set
Error message:
Message no. CO892
The selected reference operation set 50000012 is not valid on 22.12.2014.
If default values have been maintained in Customizing, an operation is generated automatically.
Check why the reference operation set does not meet the selection conditions:
Has anybody managed to get this to work before or have you an alternative method to record variances without having to manually create each step?
Regards
Paul
Hi,
First of all, Please post it in the correct space to get accurate and quick response.
And your query has already been answered in the below threads: You have to maintain the routing set in OPEB.
http://scn.sap.com/thread/671713
http://scn.sap.com/thread/1731094
Hope this helps u,
Regards,
Kiran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
90 | |
10 | |
10 | |
10 | |
7 | |
7 | |
6 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.