cancel
Showing results for 
Search instead for 
Did you mean: 

PM order status updates in PS N/W activity

Former Member
0 Kudos

Hello

We are intergating PM with PS, we have done required confuguration in "Define Order Value Updating for Orders for Projects (OPSV)" and Define Parameters for Subnetworks (OPTP).

We have now assigned PM order to Project network actvity (ADPMPS)

We can see planned cost in project report S_ALR_87013552...etc.

I have a question that, as we go on confirming PM orders (PCNF or CNF), can we have same staus updates in network actvity?

Thanks in advance.

Deepak Pitale

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Answer is No. You can only see the cost at project level, while the progress will be available in PM order.

Regards,

Mahendra

Former Member
0 Kudos

Thanks Mahendra