on 03-15-2007 3:37 PM
Hi,
SRM 5.0, Extended Classic Scenario
Step 1) Shopping Cart is created
Step 2) SC is approved
Step 3) PO is created in EBP and replicated to R/3
Step 4) PO is communicated through ALE/IDOC/EDI to the Vendor from EBP
Step 5) Vendor is "Rejected" (REJ) the PO and communicated through EDI to EBP
Step 6) Question 1) What and where will I see the rejection status in EBP
Step 7) Question 2) Will EBP "Open" the corresponding SC automatically ?
With regards,
Pranav
Hi Pranav
It should be PO Response.
If there are differences between the PO response & PO, the differences can be monitored and approved/rejected.
Best regards
Ramki
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ramki,
Thanks for your reply.
I agree that PO response can be monitored and approved/rejected.
Assume Vendor rejected the PO and I have approved the "rejection" when I review the PO response.
Will EBP "Open the Shopping Cart" to place an order again with another Vendor ?
OR
Do I need to create a SC manually whenver I approve the Vendor rejected POs ?
Pls. help.
-Pranav