Storage location in SNP planning

Former Member
0 Kudos

I know PP/DS plans at storage location level within a plant, but do SNP plan at storage location level too?

Thanks

Mono

<b>Re: Mapping ATP categories</b>

Hai Mono,

As far as I know, SNP can plan at Storage location MRP area level. I am not sure whether it can plan at storage location level, if we do not configure MRP area.

Regards,

Murali.J

<b>Re: Mapping ATP categories</b>

Murali has answered your question. Storage location in R/3 needs to be assigned to a MRP Area. This MRP Area when transferred to APO becomes a separate location (Type 1007) with its own location-products. Then you can run SNP or PPDS planning at that location without any issues.

Thanks,

Somnath

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Murali/ Somnath:

I have created a new thread for the same, I was wondering in my case on R/3 side storage location are not assigned to a MRP area, that means I cant plan my storage locations in SNP?

Thank you

Mono

somnath_manna
Active Contributor
0 Kudos

One line answer would be "NO".

But what is the usage of these Storage Location on R/3 side.

How do you want to map them for planning in APO?

Thanks,

Somnath

Former Member
0 Kudos

Somnath:

I am taking in regard the MRP elements of MR (Mat. reservation/ as requirement) and UR (Stock tranfer reservation/ as replenishment) and these are maintained currently in R/3 system.

Regards,

Mono