During CJ8G one settlement error gets repeated with error msg EBP603 as follows:

Item 001 WBS element W.00000010.001 budget exceeded

Sender: ORD 540000008932

Item 001 WBS element W.00000010.001 budget exceeded

Sender: WBS U.80026507

Item 001 WBS element W.00000010.001 budget exceeded

Sender: WBS U.80010284

We find the same WBS in all the lines. What can cause this same line to reappear again in all lines.

Accepted Solutions (0)

Answers (5)

Answers (5)

MTerence
Active Contributor
0 Kudos

Hi Suman,

I guess this is due to different sender is different.

If you have a single sender, then it will display only one message.

Regards

Terence

Former Member
0 Kudos

Hallo Maria,

the issue is that the error messages does not seem to have any reason at all,

an example would be

        Sender: WBS CPX.000XXXXX-F1                  
BP604 Item 001 WBS element C14.XXXXX-F2 budget exceeded                          
BP604 Item 003 WBS element C14.XXXXX-F2 budget exceeded                          

However CPX.000XXXXX-F1 is in no way related to the receiver C14.XXXXX-F2, it is not in the same structure, it has a settlement rule to an AUC and since it does not have any other errors it is expected that settlement would take place.

MTerence
Active Contributor
0 Kudos

Hi Suman / Jacob,

There are couple notes available in SAP. Please find below, check and let us know whether this resolves your issue.

1742941 - Unjustified error messages for availability control


1606591 - Unjustified error messages when entering budgets or releases


1464000 - Unjustified error messages of availability control


In case if the above does not solve or not related to your SAP version, you need to raise a OSS note to SAP to resolution.


Regards

Terence

Former Member
0 Kudos

Good Morning Suman,

have you had any joy resolving this as we are having the exact same issue.

During execution of settlement run in background whenever the message BP604 is correctly raised even once this message is repeated over and over again for a single WBS element.  This occurs even though the WBS element is only maintained as a settlement receiver once.

Former Member
0 Kudos

This message was moderated.

sanjeevc
Active Contributor
0 Kudos

Go though any of structure report as cns41 as well and select the fields for budgeting and actual cost and plan cost.

do comparison as below:

Plan Vs Actual

Budget Vs Actual

Report will show if budget exceeded? make adjustment then execute settlement.

Regards,
Sanjeev

former_member299514
Participant
0 Kudos

Hi

Understand your suggestions but my querry is why this error gets repeated for the same WBS in all error lines. This is in almost 50 lines and whatever may be the sender object of the cost the error always shows for the same WBS. Since this a standard program do we still need to look deep into the code?

sanjeevc
Active Contributor
0 Kudos

Now you are saying this is standard code then may be some Consistency but i guess local ABAP couldnot be help on it, so please raise the OSS to SAP.


Regards,

Sanjeev

former_member203098
Active Contributor
0 Kudos

Hi Suman,

In project hierarchy lower level wbs elements and activities are settled to the respective higher level WBS element. In standard when we execute collective processing of settlement, system considers all the cost objects in the hierarchy which have settlement rule and does the settlement to receiver. In your case the wbs W.00000010.001 is reciver for many lower level objects.that's why same wbs is showing multiple times in the error message with different senders.

Check the budget exceeded issue on the WBS element W.00000010.001 as suggested by Tushar and Sanjeev.

Regards,

former_member299514
Participant
0 Kudos

In my case the sender objects are from different projects.

former_member203098
Active Contributor
0 Kudos

Hi Suman,

In settlement rules receiver are maintained as Wbs W.00000010.001 for many cost objects, though senders are from different projects. resolve the budget issue and execute the settlement you don't find the multiple error lines on the receiver wbs element.

Regards,

Former Member
0 Kudos

Hello Suman,

Go to Budget report S_ALR_87013558 for WBS element W.00000010.001 and check how much is the available amount against Budget.

Check Actual cost and open commitment for this WBS element.

You can check list of open commitment from CJI5 report as well.

Regards

Tushar