KEPM - COPA Planning, planning done and manual distribution has been done
but Plan is not able to transfer to SOP
kindly advise for the same
KE1E - Transfer Plan to SOP generate message as Editing done successfully
but when i am checking in MC83 on product group level this transfer is not able to get over here
please advise for the same
highly appreciate for quick response
thanks in advance
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I'm trying to explain some options that you have to configure massive planning in CO-PA.
Yes, it's possible to have this data automatically! I could think in 2 options when you work with KEPM.
1) Create Planning Layouts to Upload quantities, prices, etc to the characteristics (KE14). Thus, you will be able to upload Excel file with quantities/prices values by material and customer.
2) Another option is import the quantities from SOP / LIS info structure by material and customer.
See more in IMG > Controlling > Profitability Analysis > Planning > Integrated Planning > Define LIS Interface.
In this step, you define the interface for transferring data between info structures in LIS and operating concerns in Profitability Analysis (CO-PA).
This interface lets you transfer the following data:
Activities
In the characteristic assignment, you assign the characteristics in the info structure to characteristics in the operating concern.
In the key figure assignment, you assign the key figures in the info structure to the value fields and quantity fields in the operating concern. Here you can only assign quantity fields to quantity fields and value fields to value fields.
Under assignment groups, you essentially enter the desired operating concern and the corresponding info structure, plus the assignments of characteristics and value fields.
Further notes
When you tranfer data from SOP, you do not need to make a characteristic assignment because this is already defined in the system. The assignment is defined as follows:
CO-PA -> LIS
WERKS -> WENUX
ARTNR -> PMNUX
WWxxx -> PMNUX
The field WWxxx stands for a user-defined characteristic that corresponds to the product group in SOP. When you transfer data from SOP to CO-PA, the system determines whether the characteristic value in the field PMNUX is a product or a product group. If it is a product group, the system uses the corresponding field in CO-PA based on the master data for that product group.
For info structures that are copied from the SOP info structure S076, you can only transfer data at the product or product group level and at the plant level. The system summarizes the data over any other characteristics.
BR,
Chandresh Vyas.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Chandresh,
We are transfer planning figures from CO-PA to SOP and we would like Planning Plant (at Logistic level, distribution centers) to be aggregated in Production Plants, i.e. in CO-PA we have DC 1000, 2000 and 3000 and we would like to transfer those figures summarized in Plant 9999.
Any ideas to do that?
Thanks in advance for your support,
TP
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.