Progress analysis for project without Project Version

Former Member
0 Kudos


HI PS Gurus,

Need urgent help !!

Is it possible to use Milestone trend analysis for Progess analysis without creating project version. Also is there any method for Progress analysis without creating project version.

My project has only WBS no activities, i have put the dates and milestones with % of completion, i have put actual dates in some milestone and i  used MTA expecting to get planned Vs actual trend but it didn't happened.

My requirement is to get a progress analysis with Planned Vs Actual.

Regards

Prabhat

Accepted Solutions (0)

Answers (2)

Answers (2)

uday_sapps
Explorer
0 Kudos

HI Prabhat,

To user MTA the prerequisites are:

  1. Flag the corresponding milestones as being relevant for Trend analysis.
  2. On the chosen report dates create project versions, which also have the Relevant for MTA indicator set (at least one version is necessary for MTA).
  3. Reschedule if you want to use data from the operative project or a simulation version and update this data.

for more details click on Executing the Milestone Trend Analysis - Project Progress - SAP Library.

Regards,

Uday K

sanjeevc
Active Contributor
0 Kudos

Hi,

  • Check which-one measurement method is using in project progress?
  • that measurement method is assign to it's default value?
  • As per your business scenario milestone measurement method might be for above two point!
  • check with suggested above setting and let me know?

Regards,
Sanjeev