Unloading point v/s Route Schedule

Former Member
0 Kudos


Hi,

I got very strange issue today.

I maintained in Customer master under Unloading point tab , a unloading point with factory calendar.

When I used this customer to create SO(Sales order) , then the Route Schedule is not appearing in SO.

But, once i removed the unloading pont-factory calendar from customer master, then Route Schedule is appearing in SO for that Customer(Ship-to-party).

Is it a standard behaviour of SAP or am i missing something.

Thanks

Neha

Accepted Solutions (1)

Accepted Solutions (1)

JL23
Active Contributor
0 Kudos

go through the checklist that can be found in KBA 1750978 - Route Schedule does not populate on sales order

Former Member
0 Kudos

Thanks Jurgen.It solved my issue. we need to maintain in Route schedule also the same unloading point as maintained in customer master.(For this case).