QM Early Inspection Lot 04 Not Created


I am attempting to create an early inspection lot for type 04 related to a production order.  I have assigned and activated 04 inspection type to the material master.  I have set the Control for Insp to Early Inspection lot for order item.  I have defined the necessay production master data for BOM's and Routing and I have define and inspection plan for type 5 Goods Receipt that is release, has Master Inspection Characteristics assigned and the check produces no mesages, wrnings or errors.

I manually create a production order for a quantity and schedule the order.  The BOM and Routing are pulled in without issue.  When I release the order, I do NOT see the Preparing Quality message and when I save the order.  The routing is one step so no confirmations have been made yet but parts are being produced so I go to results recording QE51N for the material with inspection lot origin 04 but no lot is presented for results recording.  I would expect to see the early created lot.  Any suggesttions are appreciated.

BH

Former Member
Not what you were looking for? View more on this topic or Ask a question