Hello! When I distributing contract from SRM to ERD, I have error in BBP_PD "Distributing incorrect". In RZ20 I have error "Different processing times defined for BLAORD and CONDA" "Application error in back-end system ERDCLNT700 (SAP SRM outline agreement 4400000137)".
In ERD I have no any errors in BD87, SMQ1/SMQ2, RZ20. I have no IDocs. And I dont have idea what to do.
Hi,
Some initial Questions from my side.
1. Which SRM version are you on?
2. What is your erp version defined in System Landscape system type?
Note : If its above erp_4.0 then Contract goes via webservices and SA via idoc , otherwise everything goes via idocs.
3. What are you transferring Contracts or Scheduling Agreements?
Note : If Central Contract - It gets transferred via webservices ( PI/Non PI) and if its SA then it gets transferred via IDOCS ( distribution model needs to be created in ECC) all this for SRM 7.0 and ECC EHP4 onwards.
Regards,
Naveen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Please check in ERP transaction WE20, that the partner declaration for your SRM System is active. This caused this error for me once.
Open "Partner Type LS" in the "Partner Profiles" tree and select the logical system of your SRM system. On the right side in tab "Classification" the partner status should be set to "A" (active).
Kind regards,
Karsten
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check partner profile settings for message types BLAORD and CONDA in both systems.
Regards,
Sheetal Chawda
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.