Hi,
I have a big problem in project plannig board.
In project planning board, table area and timescale assistant are broken.
In fact, I already asked that problem.
But I made some misunderstanding in my qustion.
My SAP GUI version is 730 and patch level is 5.
And our system is non-unicode system.
When I am using classic theme, there are no problem,
But I am using other theme, all has broken.
The 'theme' means not Windows theme.
It means SAP GUI Theme. ( At this point, I made misunderstanting )
I tried and tried, But I can't solve this problem.
Please give me a suggestion or some tips.
Thanks
Hello Jun,
Please check following SAP notes can help you.
355618 - CJ2B: Missing or wrong texts in Planning board assistant
500933 - Proj.plng board: Recomm., additional information, consulting
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.