Dear all,
We are planning to upgrade the SAP ERP system Enhancement Package6 in ECC6.0 ERP system.
Source ERP: ECC6.0
Target verions: ECC EHP6
1) Is there any impact of other environments[BI, PI, & Solman] depend on level of applied EHP6 Version in ERP system.?
2) Is there any impact in design of connection with other SAP system like Connecitivity to the SAP solution Manager sytem ,Centralized user management, PI system?
3) Is it necessary to upgrade the (ST/PI, API) in Solution manager ?
Thanks Thiru.
You can run the Analyzer (CIA - Change Impact Analzyer) in Solution manager. Yes there will be impacts because there are object additions and changes. We just did a major upgrade, (19 upgrades behind! ) across IS-U, CRM, BI, PI and NWJ and in each of these we had to make adjustments. Use Solman, it will save you lots of tears.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please ref: the below link.
1. Grenerate Stack XML for target level. The Upgrade Dependency Analyzer (UDA) can support you in planning your next upgrade.
2. No impact in connecitivity to the SAP solution Manager sytem ,Centralized user management, PI system.
3. Keep your ST-A/PI or St-PI to latest level
BR,
Prabhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prabhakar,
Thank you for your reply.
3. Keep your ST-A/PI or St-PI to latest level
OK we will update the lastest ST-A/PI or St-PI version during EHP6 upgrade.
My question is, because of EHP6 upgrade only ERP system.
1) Do we have to upgrade [ST-A/PI or ST-PI] in Solution manager or not?.
Thanks
Thiru
Hello,
1) Please refer to SAP note 1388258 - Version Interoperability within the SAP Business Suite
2) No, there is no difference in design of connectivity.
3) It is always recommended to upgrade ST-A/PI or St-PI to latest level.
Thanks,
Sunny
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sunny-san,
Thank you for your reply.
Here we have the following SAP Systems in our landscape.
1)Solution Manager server [ EWA, SM,BPM and CUA with all below SAP servers]
2) ERP system 6.0
3) BI system 3.5
4) PI 7.0. We are planning to upgrade only ERP system 6.0 to EHP6.
1)In this case, after EHP6 upgrade, Is there is any impact of solution manger or
2) Is it mandatory to update Solution Manager [ST-PI and ST-A/PI] version?.
Thanks Thiur
Hi,
First of all please used the below tool to check the dependency.
Thanks
Rishi abrol
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
10 | |
10 | |
9 | |
7 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.