Dear Experts,     

I'm facing an error while executing Product Heuristic in /SAPAPO/RRP3.

I'm getting a message "capacity requirement is invalid" with message no as /SAPAPO/OM601

I've checked the capacity requirement in ECC workcenters, as mentioned into SAP help,  which seems fine.

I'm using control key PP01 in my routing. May be I'm still missing something, Pls help me to find what else to check...

Regards

Accepted Solutions (1)

Accepted Solutions (1)

former_member189901
Contributor
0 Kudos

Hii Dennis,

Check may be the resource is assigned as Multi resource where as capacity is maintained as 1. If it is muti resource then capacity should more than one. Oe else change the resource to single/single mix resource...

Hope it clarifies your issue...

Regards

Debashis

Answers (1)

Answers (1)

former_member458819
Active Participant
0 Kudos

Hi

A capacity requirement has an invalid value. Depending on the resource used
and the type of the activity, the following values are valid:

  • If the capacity requirement is to be scheduled for a single resource,
    it must have the value 1.

  • If the capacity requirement is to be scheduled for a multiresource,
    it must have a value greater than 0.

  • If the capacity requirement is assigned to an SNP activity, it must
    have the value 0.

  • If the capacity requirement is to be scheduled for a resource without
    time-continuous capacity
    (for example, a bucket or transportation resource),
    it must have the value 0.

Sunil