Dear Gurus
A solution is needed for the secnario described below.
Quality inspection lot origin 04 is created when our production worksheet gets confirmed.
The materials are consumed thru backflushing with movement type 261.This is a zdevelopment.
The production supervisor commits some mistake while entering which is identified later, the reason
being wrong production version, or wrong material entered.
Meanwhile the quality personnel has entered their test results against each MIC of the material having
different batch nos in the inspection lot.
To rectify the error , the production supervisor will be creating a new worksheet with the correct entry
and confirms the worksheet , triggering creation of another new inspection lot.
The quality people doesn't want to re-enter the results in the new inspection lot if the material is same
They want all the results of the old inspection lot to be copied onto the new inspection lot against each batch.
The old worksheet is cancelled and the material consumption are withdrawn with movement type 262
The results of th inspection lot(wrong) should be copied to the new inspection lot created only when the users comes across this situation.
tried doing it , but not able to succeed , because for each inspection lot entry, it is asking for the
source inspection lot, and the results are not getting copied.
Is there any way to do this only when required for copying.
Pls help.
Regards
Vidhyadharan
Hi,
Pl go through following link to know about all the prerequisites.
SAP Library - Inspection Lot Creation
ntn
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nitin
I tried, but when I do QA32 RR - for each Inspection lot, the popup comes why. I should be able to select a inspection and copy to another inspection lot. In customizing "Make settings for copy of inspection results" I have made the below entries.
Inspection Type : 04
Plant : 1898
Control in inspection lot : 3 Manual and automatic posting
Control in RR : 3 manual and automatic data transfer
close check box ticked
Origing TL : Batch valuation
DatOrig.RR : Batch valuation
selection : 300 custom selection of inspection lot
mapping : 200 Master Insp.Characteristic and method
When I select the inspection lots (QA32) I have two inspection lots one is old(say a) with system status
as INSP RREC SPRQ and a new one (say b) with system status REL CALC SPRQ. I have entered some results in lot A which I want to copy to Lot B.
Hope I am clear .. if not please do post your questions
Regards
VIdhyadharan
Why are you using batch valuation? You do not want to copy the results from the batch record to you? Try 02 or DatOrig.RR and Origin TL.
For control in RR use "Manual Start of Data Transfer". Then the user can start the process themselves when they are in results recording from the Menu bar.
Craig
There could be one reason then if all other settings are correctly maintained.
MICs for which you want to copy the results from other inspection lot, pl check if you have maintained the 'Origin result data' ?
if not, go to QP02, select the required MIC>> General data details>> Origin result data>> Previous inspection lot and save.
Now create two fresh inspection lots, enter results in first & save. Now go to next inspection lot>> edit>> Copy inspection results>> enter first inspection lot number.
You will get the result copied to this inspection lot.
ntn
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.