Test Plan - STWB_WORK - Unable to change.

Former Member
0 Kudos

Hi all,

When I execute the test plan using the transcation stwb_work, am unable to test it and giving a message "Test plan is protected against all changes".

Could anyone help me on this?Help will be greatly rewarded.

Thanks

Ro

Accepted Solutions (0)

Answers (3)

Answers (3)

prakhar_saxena
Active Contributor
0 Kudos

Dear Friend,

Please go to transaction STWB_2

and here choose the test plan by F4 and then goto Attributes

Here go to change mode and then make status as RELEASE - release the test plan ,for testing.

Regards

Prakhar

ApurvaKshr
Discoverer
0 Kudos

Hello Prakar,

Edit button is disabled.

Regards,
Apurva

Former Member
0 Kudos

Hi,

I would like to know how did you execute the test plan ?Do you click on any icon or tab to execute it.If yes, how does the icon resemble ?In our case only 1 icon is displayed(resembling a document page) under test case description tab in stwb_work tcode.

Regards

Imaan

Former Member
0 Kudos

Hello Rob,

please check in the attributes of that test plan. Someone has set it to protected there. You will be able to unprotect it there too.

Best regards

Juergen

Former Member
0 Kudos

Can you tell me where to change the attrubutes?I selected the test plan and went to Goto - Test Case attributes nothing happens.

Thanks