Hi All,
Request your help:
I have an item created and linked to WBS element. WBS has actuals posted, when i run the program to transfer the cost - there is an error mentioning "No link exists between SAP PS Project element and selected SAP PPM items"
can you help me which setting is missed.
thanks
Hi,
did you check which logical system is linked to your project management in customizing? This has to be the logical system of the ECC system.
Yours,
Miel