Maintenance Plan Scheduling

Former Member
0 Kudos

Is it possible with maintenance plan scheduling to generate a work order based on the preceding work orders confirmation/completion date? The preceding work order confirmation/completion date would be the new work orders plan date (in line with the maintenance package frequency). Have tested the maintenance plan call parameters without getting the desired results.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

From what you describe I think it should be possible when you switch the "completion requirement" indicator on and set the tolerances to 0 % and shift to 100%.

best regards,

Ruud