Customer planned requirements key figure in OFM

Former Member
0 Kudos

Hi ALL,

I am trying to send demand (Purchase requisition) in OFM in customer planned requirements key figure by using the report RSMIPROACT2, however I am unable to see the data in customer planned requirements.

Kindly suggest if any exacts settings for the same or if any other process to be followed

Thanks

Gaurav     

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Gaurav,

Check the following after you run the RSMIPROACT2 report in ECC:

1. PAN XML has successfully been trigerred out of the ECC system

2. PAN XML has reached the SNC system and has been processed successfully.

3. Go to the XML payload and verify if the Pur Requistions data is available for the Location product you have used.

Thanks

Bharath