on 12-05-2013 4:27 PM
Hi,
I want to know, if we activate Cross System object locking (CSOL), then do we need to wait till chnages to that particular object is delivered in production ?
I mean other chnages which involve same object changes, do they need to wait till exiting locked object moved to production.
Regards
PK
Hi PK,
This is depends how you customize it.
You can do :
By the standard customizing:
And also you need to consider lock monitor, even if UC is imported to PRD you need to delete locks manually or make project import buffer to PRD, this will refresh all locks.
Rg Dan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi PK,
Just use SPRO
CSOL provides the following categories to classify customizing error
conditions. This keeps transport objects reliable and consistent in your
development landscape and transport process. If an object to be saved violates
all the categories, an error message will appear and the object cannot be saved.
Any other conflict will be displayed as a warning message, and you need to
determine the subsequent action.
You can specify what is regarded as an error when a developer tries to save
an object, in terms of information about this object, with regard to the
criteria "Project", "Change Type Relation", and "Object Type". Only if ALL three
criteria have been met by the object attribute, an error message is
displayed.
The "Warning Only" checkbox allows the developer to ignore the CSOL error
settings. Only a warning message will appear, you can save nevertheless.
Caution: You must be aware of the risk when you choose this option.
After this activate CSOL for your dev system and client
Rg Dan