Hi Experts,
I have a 4 level BOM and routing structure.
RM1 creates SFG1 (Semifinished good 1). SFG1 creates SFG2.((Semifinished good 2). SFG2 creates final good FG1.
Kindly validate below points:
1. If I create 3 Production versions ( 1 for each -SFG1, SFG2 and FG1) then in APO corresponding 3 PDS will be created after CIFing. Is this correct ?
2. Is this best possible scenario for creating Planned Orders in APO for a material with 4 levels of BOM or it can be better? In other words -- can we create Master Data in a batter way for a material with 4 level BOM?
3. Is this possible to create a PDS which has all 4 levels in it ? (Means the PDS of FG1 has information upto RM1 level in it )
All pointers will be helpful ...
Hi Lerner,
answer
1. Yes
2. Yes if this is requirement
3. when u transfer the PDS for all. and open FG PDS.. u can keep on expansing BOM (assembly) as you do in CS03 .
what matters in APO.. are all these materials are critical? do they need to be planned in APO?
Pravin M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.