Hi Debasis,
Execute transaction /SAPAPO/RRP3.
Go to menu Settings and choose User Settings.
Go to General tab and check current Days' Supply Type
An Alert Profile has been assigned to your user
This Alert Profile has Days' Supply Types set
In standard, when Days' Supply Types are maintained in the Alert Profile, the Days' Supplies from the Alert Profile are always used.
The days' supply specifies how long this available quantity can cover the expected requirements.It indicates when the available quantity becomes negative for the first time, if there are no future receipts. Please check the same you have valid receipts to cover the requirements.
Also refer the help link,
http://help.sap.com/saphelp_scm70/helpdata/EN/39/24a037f11cff7fe10000009b38f889/frameset.htm
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rupesh,
Thanks for quick reply . We are using Alert profile and want to let you we are using a BADI /SAPAPO/RRP_COVPARAM that is used for calculating the days supply type in product view. 9999.9 is the maximum duration maintained in days.I have noticed that if there are no elements for a product in product view the initial value visible in all the days supply type is 9999.9. And also if there is surplus stock for a product, days supply type takes the maximum value.
I reduced the stock to negative value at that time the Days supply type is populating a value.
So just to know that is this a standard thing ?and if it is then how its calculating the value ? Is there any formula.
Hi Debasis,
This is correct behavior according to SAP standard design. Please note quantity which is pegged via fixed pegging links is always covered; they do not participate in the calculation of the Days' Supply.
You can use BADI /SAPAPO/RRP_COVPARAM (From SAP Note 1027082) to influence the results of Day's Supply calculation
Day's Supply Type in defined in SAP customizing (T-code /SAPAPO/RRP_CVTYP).
SPRO -> Advanced Planning and Optimization
-> Supply Chain Planning
-> Production Planning and Detailed Scheduling (PP/DS)
-> Order View
-> Define Days' Supply Types.
Regards,
R.Brahmankar
This values shows there are receipt elements with no requirement.
or no receipt and requirement element.\
Please press F1 on the field and understand what is mean by Days' supply. you will understand why such huge values.
Thanks
Pravin M.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.