on 12-04-2013 1:45 AM
Hi All,
We tried creating a PO with multiple PRs but no PO number is generated. I checked PR details but all items are verified correct except for some delivery date of SAP PRs which are already passed due. Out of 5, 4 PRs have deleted POs which are also created in SRM.
Lookinf forward to your immediate response.
Thanks and Regards,
Hi,
Check the workflow status at transaction SWIA
Senthil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Did you check RZ20 transaction? is there any error?
Which is the status of the SC?
Did you try to transfer manually with BBP_PD_SC_TRANSFER MF?
BR
Emanuel.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.