on 12-03-2013 11:41 PM
Hi,
we had the same problem after our update to EHP7.
We could solve it by implementing SAP note 1882238.
Regards
Markus
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Actual GI date can be disabled through SHD0. For details steps you can refer the below tread.In your case also may be your company has done the same by not modifying the Actual GI date by the user. As already said system copies the current date as actual GI date if we don't enter any date manually in actual GI date.
thanks,
Srinu.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Actually ,once you complete creation of delivery ( PGI ) then actual GI date will be automatically update.But in your case it is going in grey mode at VL02N level it seems ,some enhancement might be done in your case,not sure also.If you take ABAPer then it would be helpful to you.
Thanks,
Naren
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for the responses Naren and Srinu,
We recently went through a SAP stack upgrade after which graying out of Actual GI Date has happened. There is no problem PGI'ing Deliveries but this functionality should be restored. It doesn't look like its because of a system enhancement (as there was none related to this before or after the stack upgrade and it worked just fine). Can this be resolved by some SAP note?
Thank you