Commitment Cost of S_alr_87013558 and CJI5

former_member228466
Participant
0 Kudos

Dear Team,

I come across an issue that using T-code S_ALR_87013558 I m getting the commitment cost  but when i want to see using line item wise T-code CJI5 system showing blank.

Please specify the reason behind and also i want to make the commitment cost zero,Is there any process that i can select multiple PO and Click on Deliv Comp.

Regards

Soni

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Yogendra,

I think it is not possible to select multiple PO and Click on Deliv Comp.

Secondly, commitment inconsistency can occur if line items table (COOI) does not get in sync with Total Level table (COSP)

Try running correction program RKANBU01, RKACOR04 ( Check SAP Note 21649).

After this try executing CJEN & CJBN and observe the results.


Regards

Tushar

Answers (1)

Answers (1)

former_member195427
Active Contributor
0 Kudos

Hi


I come across an issue that using T-code S_ALR_87013558 I m getting the commitment cost  but when i want to see using line item wise T-code CJI5 system showing blank.

Try out with a different (standard) layout and make date field as blank then check. Also,try the same after executing CJEN & CJBN.


.. and also i want to make the commitment cost zero,Is there any process that i can select multiple PO and Click on Deliv Comp.

For multile selection you have two optons:

1.LSMW or BDC (followed )

2.Edit in Table (EKPO ,Field ELIKZ)  but it is not recommended.

Regards

Saurabh