Hello,

I have created template project in solar_project_admin in 7.1. My problem is i don't know which logical component to use in system landscape as my client has given directly solution manager system to me.

I am creating scenarios for HCM,FICO,MM,SD etc modules manually in solar01 which are using sap system SAP ECC 6.0.So what should i do?

Can i use standard sap ecc 6.0 component? also i don't know what are the different systems to be assigned to this logical component.

There is no basis guy available who set this system.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Thanks Prakhar. Add me on linkedIn i sent you a request.

prakhar_saxena
Active Contributor
0 Kudos

Hi Abhishek

sure...kindly close the thread as answered if you got the answer

Thanks

Prakhar

prakhar_saxena
Active Contributor
0 Kudos

Hi Abhishek

check my article

http://scn.sap.com/docs/DOC-49474

In general you can use the standard also and can later replace it with actual logical component

in one logical component you need to maintain the various roles for the ECC or a system landscape. But definately you need to have a basis guy doing this as they need to map this into lmdb/SMSY etc as per Transport Path setup between these system and also RFC needs to be created.

let me know if you have doubt

Regards

Prakhar

Former Member
0 Kudos
Former Member
0 Kudos

Thanks Kamil for guiding me i found this link very helpful.