Dear Sirs,
I am having a situation where in same material is being sourced from 2 vendors.One having a Delivery time of 5 days and other having a delivery time of 25 days.I shall not be able to maintain the average time in material master Planned delivery time as it will give incorrect result.
I am having a MRP quota scenario,I need vendor specific Purchase requisition with the delivery time being picked from his vendor master.Also please note that I am maintaining Purchase Organization level contract and not individual Plant-material level info record.
Please help
You are in the wrong forum. You want be in MM. You need to use a purchasing information record and maintain the delivery lead time there ME11/ME12/ME13