on 11-28-2013 11:41 AM
Hi All,
Can you please tell me the table for budget distributation Date in SAP PS ( when budget distribute to Project from Investment Program Position ).
I have checked in BPGE, BPEG, BPJA table but Date field is showing blank. Is there any other Table in PS/ IM from where we can find out the budget distributing or allocating date ??
Thanking You
Rofique
It has resolved. I have used Table PRPS, BPEG and BPBK.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Kindly check in IM related tables also. May be you would find something useful there.
SE16-> IM* -> Here, check which tables gives your required data and let us know also.
Thanks & Regards
Saurabh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As the budgeting will be done on project objects only either annual/overall , I feel there are no table that will display the budgeted date directly.
The alternate way is to get the system status BUDG set date on the object & display it .
Hope this information helps.
Thanks & Regards,
Vadiraj K
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.